Atamurat-Imamnazar Road Rehabilitation Project
PPTA: TKM36074-01
Location
Turkmenistan
Sector
Transport and Communications /Roads and Road Transport
Initial Listing
3 April 2002
Most Recent Update
3 April 2002
Executing Agency(ies)
Cost and Financing Plan
(in US$)
Source
Amount
JSF
150,000.00
Total
150,000.00
Description
Rehabilitation of 115 km of the road from Atamurat to Imamnazar.
Thematic Classification
Economic Growth
Poverty Classification
Others
Objectives and Scope
To rehabilitate the 115-km road from Atamurat to Imamnazar to facilitate the flow of humanitarian aid to Afghanistan and cross border trade between the countries.
Policy Dialogue
Environment Category
:
To be determined.
Procurement
Contacts
Bank
Sean M. O'Sullivan
Principal Infrastructure Economist
ECID
Tel. No.:
(632) 632-6443
E-mail:
sosullivan@adb.org